Wednesday, April 28, 2010

Numbness Left Side Of Face Fast Heart Rate

finger is there!

Finally we go - day 1:

We have the 16th KW took a holiday, to register callback what the first 3 days so it all happens. On Monday and Tuesday we do errands and appointments to each other. On Wednesday we went wirklichlos.

The night before the adjustment date of our house was quick to Sven to end. Around 1:30 he could not sleep. Michaela was even briefly awake, but could not fall asleep without a problem.
Sven from 1:30 then wrapped up the digital and video camera, tripod and chargers, as were never absent, of course. After the alarm rang

for Michaela, Sven has already been ready to go. Clock should arrive by 6, the assembly team. We are about set off by 5 clock had to because we remove the stones already on the site of the sealing cardboard and make the water supply.

When we turned onto our street, we have seen, it was all lit up. It took a brief monent, until we realized that it was a finger house trucks already there. It was at this time just 5:15 clock.

The construction team also came a little earlier. At 6 clock They had put their tools on the base plate and prepared everything for the first wall element. At 7:30 the first wall clock was made. At 8:40 clock all 11 wall elements of the ground floor were made. That was very impressive how quickly, accurately recorded and the installation team have done the work.

went to the inner walls of the ground floor is the ceiling panels. First, the item was placed for the winter garden. This turned out to be very difficult, as this element had no guides, to place it exactly. Now the ruler had to be stopped be to ensure that the ceiling element is positioned symmetrically. It had cost a little time and nerves. Also, the assembly team!

Now came the ceiling panels above the living room. There is then noticed that the central ceiling light with double the main I-beam could not be connected properly to the ceiling panel from the winter garden. The fault was there at the Factory House fingers. These were offset by about 4 cm. After discussion by the assembly team with finger house was found an easy solution. The double T-beams in the conservatory must be postponed cm to about 4.
had
Thus, the painstakingly taught ceiling element to be removed from the conservatory and the support can be moved. This done, the winter garden element has been aligned again. Now, the two ceiling panels bolted and the ceiling are made ready. In the attic it went

as usual. The assembly team had put only time the outer and inner walls on day 1. The roof panels could not put the lack of time man. It was already 21:00 clock. The weather was not the first Aufstelltag meant well. It was very windy and it had rained slightly irregularly. The temperatures were around 5-7 ° C.


second Tag:

On 2 Montagetag house we had our finger on the weather conditions improved. The work went on without difficulty. After the ceiling panels were in the house, we just looked at the rooms in the attic. Ua, we are a ladder to the loft went up. We decided to plan for any floor stairs, since we had not thought it would ever have enough space there. After we had seen how much space we have in the pitched floor, the decision was clear. We still need a loft ladder!

The same day, even the electricians were there. They asked us if we do not change. We then went through the plans again and have changed little things. When asked if we had no shade for the winter garden, we denied this. The electrician we pointed out that a subsequent change is very expensive. He still had good ideas to improve our planning.

parallel to the Electricians began a tour of the assembly team to build the carport. Which we have also been very pleased. Sven was not sure if the color of the right was. We have bemusternt the process of sampling the eaves in the RAL 7016. This is a dark gray color. This is the same with the window color. At the end of the 2nd

Day we celebrated the topping out yet. This is one of them. But unfortunately, less and less desired by the owner, so the installation team.


third Tag:

We had an 8 clock a meeting with our construction manager, Mr S.. Mr. S. gave us a detailed flow chart the steps in which our house will be expanded. A moving in date we have received. If everything goes normally, we can move on 02.07.2010. We then asked Mr. S. first if the small color defects to be eliminated. Finger House passes the house in the RAL colors always twice. Once a plant and once at the final assembly of the house. Then we have

told our supervisor that we do not have a floor staircase and conservatory blinds. After consultation with our specialist consultant with finger housewife A., we get a quick idea of the price additional costs. We then immediately gave an oral contract for the execution of the changes given. Once again, many thanks to Mrs. A., who informs us in a hurry as always, very good. After 4 hours we were with the site manager by appointment.

Pfeiffer The company was also on site and had a look at the statics if everything was done correctly. After a little static base rate was the structural engineer

gone again. All right.
Our roof tiles have also come. On Monday, we then covered the roof finished.
We would also like to thank the other readers of the assembly team for the great work. Sven was very surprised how quickly and cleanly is worked. Thanks to Maik, Steffen, Andre and Ulf.
We also have a few pictures. We were already angsprochen by some, when the images are seen. We were all on the ground floor 3 Monday and therefore could not fill the blog with the Contour house. We now change.





Tuesday, April 20, 2010

How To Make A Metalcore Wheel

tour of the production - but where was our home ... Our home can

... already on the truck. :-)

Today was the day. We drove today to Frankenberg to watch our house in production.

As we were led by Mr K. through the halls, we quickly determined that no item had more in production. Unfortunately, as with finger home something went wrong. We also do not know if our items were brought forward. Of course we did not find that beautiful, Sorry, but we do nothing. 1 h. Access in vain. On the way back we used to go for something to eat.

Nevertheless, we have some pictures for our readers.

In the first picture you can see how the beams and elements are positioned in the house. Anscheind only understands the assembly team.



The item is a late night roof of our conservatory and also the ground from the balcony.



The truck Bodies, we have found with our name on it. Links are our ceiling panels and the right is the roof structure.


One of many truck bridges. There will be at least 4 trucks. But rather 5 because we have a double carport at the house.



Here is a look not packed truck bridge out of our house wall to the carport.




Hm, could this be our winter garden element?



Yeah, right. This is one of three elements of our winter garden.



The following picture shows a wall element from the inside. Installation and preparation are all available in the CORRECT :-).




On the way back while eating we were approached by the parents, the we should sprout the construction sites once.


Why should we do it? We have seen it then quickly and amazed. The crane was set up ready. And the crane driver wanted to have power only to watch television. But Also Brian.



Sunday, April 18, 2010

Oxford Level E 4-6 Review Answers



So, we have now provided, according to construction and specifications our clients performance and have the bottom plate sealed with the sealing system of Knauf of Katja Sprint.

how it looked earlier of:



My father came to us late in the afternoon to help. The three of it was to install very easy. So it looks now from:



We discard even small things settle to the foundation. The construction manager had recommended us something concrete to tribes to ensure that the posts securely rest on the foundations.


My wife has the same time also the drill taken in hand:



I wanted but sometimes :-)


Now, get it only two days until we reach our house. All subsequent appointments with Eon, heating and water are determined to ensure that we can also move on 01.07.2010.

the target tree, we have been worried. The nights to the control date will be determined no longer. The day before the parking time we go there again to Frankenberg to see us home production of our house. Trust is good, control is better :-).

the evening, we have only realized how intense the sun was. We both had a slight sunburn.

Friday, April 9, 2010

Not Being Awkward Around Friend You Like

finger base plate are finished setting date is

Our floor slab was completed yesterday.

how it looks now with us on the plot.


Today we received another call from finger house Our house is on 04/21/2010 to 6 : 00 Clock mounted.

We are already huge and it can not even grasp now how fast everything goes.

Everything on this blog to our Contour house.

Thursday, April 1, 2010

What Are Unemployment Certification Questions Ny

Now the civil contractors in the series

is now our fill soil there. Now you can put our civil contractors go.

preliminary but a picture of the slope of our plot. The neighbor has not filled up and is angry therefore determined later that he did not do it.

What you see on the picture is not is that there are about 1 m height difference.



working material for the bottom plate and inspection chamber:



Without gross stakeout goes nothing:



the morning we started digging the foundations. This is done in 2 stages:



First stage completed: visit



In the week 15 some finger house again. We'll look at how our fingers house goes into production. An exact date we have not yet. But we do not even hope that it will be deep in the night. Finger House works so since the beginning of the year in 3-shift operation.