Contur house are almost finished
finger house has now installed our house almost finished. But, unfortunately, is missing the external plaster. After the plaster is on it is also the balcony railing and the conservatory blinds installed.
Everything ready for the move.
On Thursday we got the house delivery. Therefore, we will go today or tomorrow, look through the house and whether all the details have been also done or what might still have been added.
Tuesday, June 29, 2010
Friday, June 25, 2010
Symptoms Hard To Swallow Lump In Throat
tilers finished
tiles are there. After 6 working days of 205 sqm tiles had been laid. All this was not only fast but also very clean all over the stage.
tiles are there. After 6 working days of 205 sqm tiles had been laid. All this was not only fast but also very clean all over the stage.
And these are the last images before final assembly on Monday and Tuesday.
bathroom
dwellings Attic:
On Thursday 07/01/2010 at 8:00 clock our construction manager will give us our dream home. From this day we are homeowners and have the responsibility.
We also hope that Mr. B. will be there. Mr. B. has advised us always great, and does so still.
on 02.07.2010, we want to move. Now there are only 6 days.
Saturday, June 19, 2010
Mother And Chilld Symbol
interior plaster finish
This week is our interior plaster finished. Now you can have the house better idea of how it once.
As a surprise in the past week we have welcomed on Wednesday even the tile in our house. However, this was only because of the floor of another building owner was not yet dry. The sooner - the better. It is now possible, the finger house our house is finished faster. It changes nothing but the Einzugstermmin.
only to the outer wall, it may perhaps take a while. Because of the long winter, the plaster work is not normally begin at other builders.
Next week, tiled finish. In the same week is the blower door Test. The heating instruction takes place and the telecommunications equipment is manufactured. A small list of defects we pass the site manager to ensure that the deficiencies have been processed to the feeder. There are no major shortcomings, but if you build turnkey, everything should be the way one wishes.
Then the following week on 02.07.2010 is our wish-move-in date. In the week the house is assembled. There are doors in and the balcony railing is completed. In the bathrooms, the sinks, toilets and showers are installed.
And here are some pictures from our house:
HWR:
spray plaster times seem:
master bedroom is not tiled:
time the roof window hochgeschaut:
living room with conservatory Tiled but without joints:
comments are always welcome. By finger-house staff. : -)
Saturday, June 5, 2010
Can Ptosis Be Repaired Without Surgery
delicious free beer ...
... and sausages. We make it taste good. On 02.06.2010 it was time. The first division spot for the DSL project Körle. We did not want to miss. There were about 120 guests followed the invitation.
In the photo left the mayor's watch from Körle. Law is the representative of Netcom.
In the background are the citizens that need to be This project has made it all possible. You have received a total of 507 letters of intent for the project together. And must therefore for the community is a unique project off the ground. The town has about 1050 households. This means that almost every household in 2nd Körle very fast Internet access at their disposal.
All preliminary agreements have ordered a speed of 16,000 get a 25 000 for the price of DSL service. We are also there. We asked on of the event, how high the cost of a DSL line is 50 000. And amazed the upgrade costs were only 5 €. For the additional cost it pays to take a DSL line with 10000 50 000 upload. This should be launched in September at the latest.
Subscribe to:
Posts (Atom)