Our district heating station is running now. The screed can come.



preparations for the screed:



A truck with anhydrite was also there on time:



The colleague at work. With the truck driver they were three.




was after about 1 1 / 2 hours even the floor in the house. We must enter the first floor, according to site manager on Friday. Then the floor is heated.




KW 20:

On Monday, the supply trenches are closed and compressed.

On Tuesday, the power connector is connected to the power column. Electrical work will be removed.

On Wednesday we will provide the loft with boards.


DSL connection:

Körle The town was until this year, very thin equipped with DSL. This will change this month. It start construction work for a fiber optic network. The community Körle has started a project to tie the community with faster DSL. All information about the project can be read on http://www.körle.de/ We can Anschuss in September, with up to 25,000 k / order bits. What we will do well :-).